Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

BCYF Gallivan Community Center

Replace the roof and gym floor, provide air conditioning in the gymnasium, upgrade the fire alarm system and emergency lighting, and upgrade the power outlets and selected lighting.

Health: Initiatives to increase access to quality healthcare and improve public health.
Location: Mattapan
Status: In Construction
Managing Department: Public Facilities Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 2,960,000 0 0 0 2,960,000
Grants/Other 0 0 0 0 0
Totals 2,960,000 0 0 0 2,960,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 11,753 2,295,970 252,278 399,999 2,960,000
Grants/Other 0 0 0 0 0
Totals 11,753 2,295,970 252,278 399,999 2,960,000