Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

RFMP Pier 6

Develop design plans for the replacement of the Pier 6 steel bulkhead.

Economy: Initiatives to improve economic mobility and strengthen Boston’s core and emerging industries and small businesses.
Location: South Boston
Status: To Be Scheduled
Managing Department: Boston Planning and Development Agency
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 400,000 0 0 0 400,000
Grants/Other 0 0 0 0 0
Totals 400,000 0 0 0 400,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 400,000 0 0 400,000
Grants/Other 0 0 0 0 0
Totals 0 400,000 0 0 400,000