Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Central Library: Piping Infrastructure

Replace and update piping infrastructure including small diameter hot water piping, chilled water, steam and condensate return piping and related valves in the Johnson and McKim buildings.

Arts & Culture: Initiatives to support a thriving, diverse arts and culture ecosystem throughout the city.
Location: Back Bay
Status: To Be Scheduled
Managing Department: Public Facilities Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 1,950,000 0 0 0 1,950,000
Grants/Other 0 0 0 0 0
Totals 1,950,000 0 0 0 1,950,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 0 0 1,950,000 1,950,000
Grants/Other 0 0 0 0 0
Totals 0 0 0 1,950,000 1,950,000