Eliot School at 585 Commercial Street

Renovate 585 Commercial Street office building, including building envelope, structural work, interior and site work, which will provide additional classrooms to support the Eliot School's expansion as a K to 8 school.

Education: Initiatives to strengthen education, job training, and career connections.
Location: North End
Status: In Construction
Managing Department: Public Facilities Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 19,800,000 0 0 0 19,800,000
Grants/Other 15,800,000 0 0 0 15,800,000
Totals 35,600,000 0 0 0 35,600,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 1,844,485 3,872,952 10,406,000 3,676,563 19,800,000
Grants/Other 15,796,587 3,413 0 0 15,800,000
Totals 17,641,072 3,876,365 10,406,000 3,676,563 35,600,000