Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Core Technology Infrastructure

Install hardware platforms to run applications supporting City business. Scope includes data center consolidation, server virtualization, business interruption planning, enterprise storage, network management, VoIP deployment, and information security.

Technology: Initiatives to make Boston’s infrastructure and services dynamic and responsive to residents' needs in real-time.
Location: Citywide
Status: Annual Program
Managing Department: DoIT
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 8,669,773 0 0 0 8,669,773
Grants/Other 0 0 0 0 0
Totals 8,669,773 0 0 0 8,669,773


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 1,119,773 1,135,000 6,415,000 8,669,773
Grants/Other 0 0 0 0 0
Totals 0 1,119,773 1,135,000 6,415,000 8,669,773