Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Building Envelope Repairs at Various Stations

Building and envelope repairs at Engine 29, 32, 37, 53, and 56.

Government Effectiveness: Initiatives to maintain or enhance the efficiency of government operations.
Location: Citywide
Status: In Design
Managing Department: Public Facilities Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 2,017,500 0 0 0 2,017,500
Grants/Other 0 0 0 0 0
Totals 2,017,500 0 0 0 2,017,500


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 100,000 150,000 1,767,500 2,017,500
Grants/Other 0 0 0 0 0
Totals 0 100,000 150,000 1,767,500 2,017,500