Fiscal Year 2019 Budget
Beginning July 1, 2018 and ending June 30, 2019
Last updated:
4/11/18
Roof and Masonry Repairs at Engine 4, 14 and 55
Roof and masonry repairs at Engine 4, 14 and 55.
Public Safety: Initiatives to support infrastructure and equipment utilized by Boston's first responders.
Location: Various neighborhoods
Status: In Construction
Managing Department: Public Facilities Department
Operating Impact: No
Location: Various neighborhoods
Status: In Construction
Managing Department: Public Facilities Department
Operating Impact: No
Contact the Budget Office:
Authorizations
Source | Existing | FY19 | Future | Non Capital Fund | Total |
---|---|---|---|---|---|
City Capital | 1,600,000 | 0 | 0 | 0 | 1,600,000 |
Grants/Other | 0 | 0 | 0 | 0 | 0 |
Totals | 1,600,000 | 0 | 0 | 0 | 1,600,000 |
Expenditures (Actual and Planned)
Source | Through 6/30/17 | FY18 Budget | FY19 Budget | FY20-23 Budget | Total |
---|---|---|---|---|---|
City Capital | 55,847 | 500,000 | 710,000 | 334,153 | 1,600,000 |
Grants/Other | 0 | 0 | 0 | 0 | 0 |
Totals | 55,847 | 500,000 | 710,000 | 334,153 | 1,600,000 |