Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Field Lights at Various Parks

Upgrade park field lights at various locations including Hemenway Park, Billings Field, and Fallon Field.

Open Space: Initiatives to strengthen our existing park system and invest in new open spaces.
Location: Various neighborhoods
Status: New Project
Managing Department: Parks and Recreation Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 0 2,700,000 0 0 2,700,000
Grants/Other 0 0 0 0 0
Totals 0 2,700,000 0 0 2,700,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 0 350,000 2,350,000 2,700,000
Grants/Other 0 0 0 0 0
Totals 0 0 350,000 2,350,000 2,700,000

Go back to Open Space projects