Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

George Wright Clubhouse Phase 2

Building renovations include installation of a new boiler, electrical system and fire protection. Update bathroom for accessibility.

Open Space: Initiatives to strengthen our existing park system and invest in new open spaces.
Location: Hyde Park
Status: In Design
Managing Department: Public Facilities Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 1,400,000 0 0 0 1,400,000
Grants/Other 0 0 0 0 0
Totals 1,400,000 0 0 0 1,400,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 38,193 75,000 1,250,000 36,807 1,400,000
Grants/Other 0 0 0 0 0
Totals 38,193 75,000 1,250,000 36,807 1,400,000