Harambee Park Master Plan Implementation

Project includes new playground on the west side of the park, and pathway, and lighting improvements.

Open Space: Initiatives to strengthen our existing park system and invest in new open spaces.
Location: Dorchester
Status: In Construction
Managing Department: Parks and Recreation Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 2,700,000 0 0 0 2,700,000
Grants/Other 0 0 0 0 0
Totals 2,700,000 0 0 0 2,700,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 34,969 500,000 1,750,000 415,031 2,700,000
Grants/Other 0 0 0 0 0
Totals 34,969 500,000 1,750,000 415,031 2,700,000