Fiscal Year 2019 Budget
Beginning July 1, 2018 and ending June 30, 2019
Last updated:
4/11/18
Area E-5 Roof Replacement
Replace the roof.
Public Safety: Initiatives to support infrastructure and equipment utilized by Boston's first responders.
Location: West Roxbury
Status: In Design
Managing Department: Public Facilities Department
Operating Impact: No
Location: West Roxbury
Status: In Design
Managing Department: Public Facilities Department
Operating Impact: No
Contact the Budget Office:
Authorizations
| Source | Existing | FY19 | Future | Non Capital Fund | Total |
|---|---|---|---|---|---|
| City Capital | 500,000 | 0 | 0 | 0 | 500,000 |
| Grants/Other | 0 | 0 | 0 | 0 | 0 |
| Totals | 500,000 | 0 | 0 | 0 | 500,000 |
Expenditures (Actual and Planned)
| Source | Through 6/30/17 | FY18 Budget | FY19 Budget | FY20-23 Budget | Total |
|---|---|---|---|---|---|
| City Capital | 0 | 50,000 | 450,000 | 0 | 500,000 |
| Grants/Other | 0 | 0 | 0 | 0 | 0 |
| Totals | 0 | 50,000 | 450,000 | 0 | 500,000 |