Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

South End Fitness Center Pool

Install a rain screen wall and added ventilation. Replace doors and exterior windows, concrete work to pool to repair leaks.

Health: Initiatives to increase access to quality healthcare and improve public health.
Location: South End
Status: In Construction
Managing Department: Public Facilities Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 1,390,000 0 0 0 1,390,000
Grants/Other 0 0 0 0 0
Totals 1,390,000 0 0 0 1,390,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 98,528 969,000 322,472 0 1,390,000
Grants/Other 0 0 0 0 0
Totals 98,528 969,000 322,472 0 1,390,000