Amory Street Extension
Reconstruct road, sidewalks, and lighting from Amory Street to the end.
Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Roxbury
Status: New Project
Managing Department: Public Works Department
Operating Impact: No
Location: Roxbury
Status: New Project
Managing Department: Public Works Department
Operating Impact: No
Contact the Budget Office:
Authorizations
Source | Existing | FY19 | Future | Non Capital Fund | Total |
---|---|---|---|---|---|
City Capital | 0 | 1,000,000 | 0 | 0 | 1,000,000 |
Grants/Other | 0 | 0 | 0 | 0 | 0 |
Totals | 0 | 1,000,000 | 0 | 0 | 1,000,000 |
Expenditures (Actual and Planned)
Source | Through 6/30/17 | FY18 Budget | FY19 Budget | FY20-23 Budget | Total |
---|---|---|---|---|---|
City Capital | 0 | 0 | 200,000 | 800,000 | 1,000,000 |
Grants/Other | 0 | 0 | 0 | 0 | 0 |
Totals | 0 | 0 | 200,000 | 800,000 | 1,000,000 |