Beach Street

Reconstruct the street/corridor from Atlantic Avenue to JFK Surface Road to Complete Street standards where applicable in order to provide safe, livable, and multi-modal city streets, including new sidewalks, street lights, trees, and street furniture.

Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Financial District/Downtown
Status: In Design
Managing Department: Public Works Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 675,000 0 0 0 675,000
Grants/Other 1,250,000 0 0 0 1,250,000
Totals 1,925,000 0 0 0 1,925,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 0 400,000 275,000 675,000
Grants/Other 0 300,000 950,000 0 1,250,000
Totals 0 300,000 1,350,000 275,000 1,925,000

Go back to Transportation projects