Commonwealth Avenue Phase 2A
Improve roadway between Amory Street and Alcorn Street by upgrading pavement and drainage conditions, improving facilities for bikes and pedestrians and widening the MBTA reservation. State and federal construction funds are anticipated.
Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Allston/Brighton
Status: In Construction
Managing Department: Transportation Department
Operating Impact: No
Location: Allston/Brighton
Status: In Construction
Managing Department: Transportation Department
Operating Impact: No
Contact the Budget Office:
Authorizations
Source | Existing | FY19 | Future | Non Capital Fund | Total |
---|---|---|---|---|---|
City Capital | 800,000 | 0 | 0 | 0 | 800,000 |
Grants/Other | 0 | 0 | 0 | 19,266,250 | 19,266,250 |
Totals | 800,000 | 0 | 0 | 19,266,250 | 20,066,250 |
Expenditures (Actual and Planned)
Source | Through 6/30/17 | FY18 Budget | FY19 Budget | FY20-23 Budget | Total |
---|---|---|---|---|---|
City Capital | 329,087 | 300,000 | 170,913 | 0 | 800,000 |
Grants/Other | 0 | 0 | 0 | 0 | 0 |
Totals | 329,087 | 300,000 | 170,913 | 0 | 800,000 |