Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Commonwealth Avenue Phase 3 and 4

Design and reconstruct Commonwealth Avenue from Packard’s Corner to Kelton Street, with the addition of a cycle track. State construction funding anticipated.

Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Allston/Brighton
Status: In Design
Managing Department: Public Works Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 2,500,000 0 400,000 0 2,900,000
Grants/Other 0 0 0 0 0
Totals 2,500,000 0 400,000 0 2,900,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 406,474 120,000 10,000 2,363,526 2,900,000
Grants/Other 0 0 0 0 0
Totals 406,474 120,000 10,000 2,363,526 2,900,000

Go back to Transportation projects