Fiscal Year 2019 Budget
Beginning July 1, 2018 and ending June 30, 2019
Last updated:
4/11/18
Connect Historic Boston
Federal Grant (TIGER) supported roadway and sidewalk reconstruction project, including improvements to Constitution Road, Joy Street, Blackstone Block, as well as a bike trail/cycle track connecting Commercial, Causeway and Staniford Streets.
Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Various neighborhoods
Status: In Construction
Managing Department: Public Works Department
Operating Impact: No
Location: Various neighborhoods
Status: In Construction
Managing Department: Public Works Department
Operating Impact: No
Contact the Budget Office:
Authorizations
Source | Existing | FY19 | Future | Non Capital Fund | Total |
---|---|---|---|---|---|
City Capital | 8,220,000 | 0 | 0 | 0 | 8,220,000 |
Grants/Other | 21,073,700 | 0 | 0 | 0 | 21,073,700 |
Totals | 29,293,700 | 0 | 0 | 0 | 29,293,700 |
Expenditures (Actual and Planned)
Source | Through 6/30/17 | FY18 Budget | FY19 Budget | FY20-23 Budget | Total |
---|---|---|---|---|---|
City Capital | 2,819,809 | 5,000,000 | 400,191 | 0 | 8,220,000 |
Grants/Other | 12,444,410 | 8,500,000 | 129,290 | 0 | 21,073,700 |
Totals | 15,264,219 | 13,500,000 | 529,481 | 0 | 29,293,700 |
Go back to Transportation projects