Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Cummins Highway

Reconstruct road, install new pedestrian ramps, enhance bike access, install new tree plantings, and improve lighting. The work limits are from River Street in Mattapan Square to Harvard Street.

Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Mattapan
Status: New Project
Managing Department: Public Works Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 0 4,000,000 0 0 4,000,000
Grants/Other 0 0 0 0 0
Totals 0 4,000,000 0 0 4,000,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 0 100,000 3,900,000 4,000,000
Grants/Other 0 0 0 0 0
Totals 0 0 100,000 3,900,000 4,000,000