North Washington Street Bridge

Design and construction of a new bridge that will replace the existing structure. State and federal construction funds awarded.

Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Charlestown
Status: In Design
Managing Department: Public Works Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 5,620,000 0 0 0 5,620,000
Grants/Other 29,270,000 6,000,000 0 178,067,519 213,337,519
Totals 34,890,000 6,000,000 0 178,067,519 218,957,519


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 4,143,717 1,476,283 0 0 5,620,000
Grants/Other 1,498,448 300,000 6,700,000 26,771,552 35,270,000
Totals 5,642,165 1,776,283 6,700,000 26,771,552 40,890,000