Washington Street / Traveler Street

Roadway improvements to Washington Street from East Berkeley Street to Herald Street, and Traveler Street between Washington Street and Harrison Avenue. Improvements include resurfacing, pavement markings, and new traffic signals.

Economy: Initiatives to improve economic mobility and strengthen Boston’s core and emerging industries and small businesses.
Location: South End
Status: In Design
Managing Department: Public Works Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 0 0 0 0 0
Grants/Other 1,500,000 250,000 0 0 1,750,000
Totals 1,500,000 250,000 0 0 1,750,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 0 0 0 0
Grants/Other 0 200,000 200,000 1,350,000 1,750,000
Totals 0 200,000 200,000 1,350,000 1,750,000