Fiscal Year 2019 Budget

Beginning July 1, 2018 and ending June 30, 2019

Last updated: 4/11/18

Crosswalk and Lane Marking Revitalization

Provide additional crosswalk and lane markings.

Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Citywide
Status: In Construction
Managing Department: Transportation Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 0 0 0 0 0
Grants/Other 2,325,000 2,325,000 0 0 4,650,000
Totals 2,325,000 2,325,000 0 0 4,650,000


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 0 0 0 0 0
Grants/Other 0 1,640,000 2,640,000 370,000 4,650,000
Totals 0 1,640,000 2,640,000 370,000 4,650,000