Fiscal Year 2019 Budget
Beginning July 1, 2018 and ending June 30, 2019
Last updated:
4/11/18
Traffic Signals at 9 Locations
Upgrade five traffic control signal locations and install new traffic control signals at four locations. Some locations require minor geometric changes to improve safety and operations. Accessible pedestrian ramps will be reconstructed as needed.
Technology: Initiatives to make Boston’s infrastructure and services dynamic and responsive to residents' needs in real-time.
Location: Various neighborhoods
Status: In Design
Managing Department: Transportation Department
Operating Impact: No
Location: Various neighborhoods
Status: In Design
Managing Department: Transportation Department
Operating Impact: No
Contact the Budget Office:
Authorizations
Source | Existing | FY19 | Future | Non Capital Fund | Total |
---|---|---|---|---|---|
City Capital | 450,907 | 0 | 0 | 0 | 450,907 |
Grants/Other | 0 | 0 | 0 | 3,036,200 | 3,036,200 |
Totals | 450,907 | 0 | 0 | 3,036,200 | 3,487,107 |
Expenditures (Actual and Planned)
Source | Through 6/30/17 | FY18 Budget | FY19 Budget | FY20-23 Budget | Total |
---|---|---|---|---|---|
City Capital | 419,491 | 20,000 | 11,416 | 0 | 450,907 |
Grants/Other | 0 | 0 | 0 | 0 | 0 |
Totals | 419,491 | 20,000 | 11,416 | 0 | 450,907 |