Warren Street and Blue Hill Avenue

Reconstruct Warren Street and Blue Hill Avenue (Dudley Square to Talbot Avenue) to improve connections to Grove Hall. State and federal construction funding anticipated.

Transportation: Initiatives to support an accessible multimodal transportation system that gets Bostonians where they need to go reliably and safely.
Location: Roxbury
Status: In Design
Managing Department: Transportation Department
Operating Impact: No


Source Existing FY19 Future Non Capital Fund Total
City Capital 300,000 0 0 0 300,000
Grants/Other 666,074 0 0 2,377,900 3,043,974
Totals 966,074 0 0 2,377,900 3,343,974


Expenditures (Actual and Planned)


Source Through 6/30/17 FY18 Budget FY19 Budget FY20-23 Budget Total
City Capital 51,509 10,000 238,491 0 300,000
Grants/Other 232,400 100,000 333,674 0 666,074
Totals 283,909 110,000 572,165 0 966,074