Budget & Management

The Budget & Management Program is responsible for the development and implementation of the City's operating budget. Program staff analyze program and fiscal management issues throughout City government.


James M. Williamson, Manager, Organization 141200

Budget & Management - Appropriations


title FY16 Expenditure FY17 Expenditure FY18 Appropriation FY19 Adopted Inc/Dec 18 vs 19
Personnel Services 550,182 486,530 593,729 663,319 69,590
Contractual Services 1,300 114,220 264,400 263,800 -600
Supplies & Materials 0 0 500 500 0
Current Chgs & Oblig 0 0 0 0 0
Equipment 0 0 0 0 0
Other 0 0 0 0 0
Total 551,482 600,750 858,629 927,619 68,990

Budget & Management
Performance Goals

Goal:

Improve use of limited city resources

Measure FY16 Actual FY17 Actual FY18 Target FY19 Target
% achieved of savings identified in budget process 0% 79% 76% 100%
% of new investments implemented 0% 0% 92% 100%
New healthcare savings achieved through the Public Employee Committee (PEC) 5.9 1.6 2.6 1.5