Building Systems - Appropriations
title | FY16 Expenditure | FY17 Expenditure | FY18 Appropriation | FY19 Adopted | Inc/Dec 18 vs 19 |
---|---|---|---|---|---|
Personnel Services | 681,753 | 714,237 | 794,039 | 834,239 | 40,200 |
Contractual Services | 1,051,595 | 1,358,463 | 1,555,328 | 1,598,177 | 42,849 |
Supplies & Materials | 28,374 | 64,408 | 54,500 | 54,500 | 0 |
Current Chgs & Oblig | 1,100 | 550 | 2,500 | 2,500 | 0 |
Equipment | 0 | 3,660 | 3,000 | 3,000 | 0 |
Other | 0 | 0 | 0 | 0 | 0 |
Total | 1,762,822 | 2,141,318 | 2,409,367 | 2,492,416 | 83,049 |
Building Systems
Performance Goals
Goal:
Maintain heating ventilation and air condition (HVAC) system in proper working orderMeasure | FY16 Actual | FY17 Actual | FY18 Target | FY19 Target |
---|---|---|---|---|
# of preventive maintenance/corrective maintenance | 80 | 42 | 80 | |
% of HVAC breakdowns corrected within 8 hours | 82% | 79% | 80% |